Project: Baton Rouge Wastewater Pump Station SCADA System August 2, 2005

ByControl Engineering Staff August 2, 2005

August 2, 2005

A method of easily converting the existing SCADA system’s 8400 I/O tag database was determined. Sample screens and database were created for the engineering review of a typical pump station. No surprises so far; converted easier than expected. Computer hardware submittals completed.

No word back on our requests for information. Will try redirecting to the next in command City engineer.

A pump station electrician met with us this past week and expressed concern about ease of maintenance and obtaining a coordinated set of electrical drawings for all new and existing station wiring. Much of this is within the scope of Phase II so largely out of our control, but we will place this on the project kickoff meeting agenda. The kickoff meeting is still on hold pending the selection of a control panel vendor and issuance of a notice to proceed to the Phase II general contractor.