Project: Baton Rouge Wastewater Pump Station SCADA System – 2006-05-23

ByControl Engineering Staff May 23, 2006

May 23, 2006

It’s taking some time for our new project manager to get his hands around all the software involved in this project. Some detail cleanup work needs to be completed at the first pump station this week in preparation for changes being replicated to the other sites.

The City is moving glacially slow at getting the PLC/HMI contract issued. Glacially slow also describes the process of resolving change order issues and getting a notice to proceed to the contractor that is building and installing the control panels. The wheels of government turn slowly….